Euronext today provided its market members with a detailed testing schedule for the migration of its cash markets to the NSC system. The migration will be completed by 29 October 2001. The new schedule was approved by all market participants.
NSC launch schedule
Test schedule
- 31 July: Completion of connectivity test
- 13 - 31 August: Partial chain test
- 15 September: Full chain test 1
- 29 September: Full chain test 2
- 6 October: Simulation of changeover 1
- 13 October: Simulation of changeover 2
- 26/27 October: Execution of changeover
- 29 October: NSC launch at Euronext Amsterdam
Euronext is pleased to announce that virtually all members have by now successfully completed the connectivity test.